Concrete retaining system beside a road
Shoring, Excavation & Earthworks

Shoring Design Solution for an Obstructing Manhole – Dubai

Client

The First Group

Location

Dubai

Completed

Nov 2024

Project Overview

Key project information

Client

The First Group

Location

Dubai

Category

Shoring, Excavation & Earthworks

Completion Date

November 2, 2024

Project Details

Complete project information

Project overview

An unused manhole stood in the line of the proposed shoring system for a tower in Dubai, next to a bridge ramp. The First Group appointed Super Arc Consultant (SAC) to find a way to remove it.

Scope of work

Geotechnical study of the manhole location.

Design solution for demolishing the manhole.

Shoring support for excavations 1.5 m to 3 m deep.

Value delivered

The design cleared the obstruction while keeping the excavation next to the bridge ramp supported.

Engineering context

Old underground structures can sit directly in the line of new shoring, especially on tight urban sites. Studying the ground and adjacent structures first helps to choose a safe way to remove them.

Related work and reading

Related projects: Bridge Foundation Protection Study – Dubai and Impact Analysis of Deep Foundations and Shoring for a Tower – Dubai.

Further reading: How excavation support and dewatering work and What a geotechnical investigation gives the designer.

Explore our Geotechnical Consultancy Services, view all group services, or send us your project details.

Back to Project Gallery

Discover more of our exceptional projects