SAC was engaged to investigate and identify the root cause of persistent construction defects in the wet areas of various apartments at the building. The defects, primarily manifested as efflorescenceوو a crystalline salt deposit caused by water intrusion, were observed on several building surfaces, the issue of seepage reoccurred in multiple affected apartments.