Project Details

Complete project information

The District Cooling Plant site faced substantial

operational challenges due to high water-table

levels and elevated salinity. These environmental

factors had a direct impact on the functionality of

the chiller plant, with water infiltration observed in

critical electrical trenches. The infiltrating water

expanded into the low and high-voltage

components, posing a threat to the plant's overall

operations. SAC was commissioned to conduct a

detailed geo-structural and Hydrological

assessment to identify the root cause of the issues

and provide actionable recommendations.